Summer Road Construction Has Begun!

As many of you have noticed, the Stolle Meadows Road #427 has been undergoing utility upgrades. This phase of the construction is now complete. The Stolle Meadows Road paving project is expected to begin August 1st, 2019. The road will be under construction from August 1 to November 6.  During that time period, the road will be closed in the work zone from 0800—1100 and from 1330—1700 Monday through Friday.  From 1100—1330 there will be a flagger to guide traffic through the work zone.  No road work should take place on weekends or holidays.  Please drive safe.

Here are the planned major milestones of the project:

  • 8/1—Logging Mobilization

  • 8/5-8/30—Tree Removal and Decking

  • 8/7—Construction Mobilizations

  • 8/7-8/16—Clearing and Grubbing

  • 8/23-10/3—Roadway Excavation

  • 9/16-10/4—Finish Subgrade

  • 10/7-11/1—Install Earthwork Geosynthetics and Aggregate Base Grading D and C

  • 11/6—Winter Shutdown Period Begins